UMUNANKWO – MPUTU – OGWANIOCHA RD
TAMAD is the contractor for this job
The Length of this road is 14.35km. Work has commenced with filling the road with sharp sand up to 9.5km. Stone base up to 9km has been done and Drains up to 4.6km constructed on both sides. Five (5) box culverts made up of two 3 box and 2 Double box culverts were also seen on site. Sharp sand filling continues and Contractor is on site
TAMAD is the contractor for this job
The Length of this road is 14.35km. Work has commenced with filling the road with sharp sand up to 9.5km. Stone base up to 9km has been done and Drains up to 4.6km constructed on both sides. Five (5) box culverts made up of two 3 box and 2 Double box culverts were also seen on site. Sharp sand filling continues and Contractor is on site